ISY-99i/ISY-26 INSTEON:Schedule
Schedule
Description
To add a schedule to a program, first select or create a program, and then press the Schedule button.
When you have finished entering the schedule information, press the [Add to 'If'] button to add it to the
'If' section of the program.
A schedule can be used to run something at a specific or between specific times.
- All/Sat/Sun/Mon/Tue/Wed/Thu/Fri Checkboxes
-
Select the days of the week this schedule should run.
- For Sunrise/Sunset, the day of the sunrise/sunset is used, but not including the time offset.
For example, A schedule to run at sunrise + 24 hours with only the Thursday checkbox checked.
This will run on Friday because the day of the sunrise is Thursday, but the offset moves it ahead 24 hours. - It is the start time only that determines whether a schedule will run on a specific day.
For example, A schedule to run from sunset to 10:30AM the next day, with only the Thursday checkbox checked.
This will start at sunset on Thursday, and continue to 10:30AM the next day even though the Friday checkbox has not been selected. - The rules for Sunrise/Sunset also apply to program 'Last Run' times.
- For Sunrise/Sunset, the day of the sunrise/sunset is used, but not including the time offset.
- Sunrise/Sunset
-
- Specify the number of hours:minutes:seconds before or after the sunrise/sunset.
- For 'To' dates and times, a day offset relative to the from date is also specified, allowing the schedule to span up to six days.
- Last Run
-
The date and time of the last run of the specified program is used.- Specify the number hours:minutes:seconds after the program was last run.